One mitigation measure may be substituted for another in a MND if:

  • The new mitigation measure is equivalent or more effective.
  • The MND need not be recirculated if the agency considers the matter at a public hearing.
  • The agency adopts a written finding that:
    • The new mitigation measure is equivalent or more effective.
    • The new measure will not cause a significant environmental impact upon implementation.

Reference: 14 CCR Section 15074.1