California Department of Resources Recycling and Recovery (CalRecycle) 

Tire-Derived Aggregate Projects

Wall 119: State Route 91 and Wall 207: Interstate 215, Riverside County

Tire-Derived Aggregate as Retaining Wall Backfill

Completed Wall 207 before placement of TDA backfill.

The California Integrated Waste Management Board (CIWMB) (now the Department of Resources Recycling and Recovery, or CalRecycle) partnered with the California Department of Transportation (Caltrans) to conduct two retaining wall pilot projects.

The first was the Wall 119 Project and the second was the Wall 207 Project. Wall 119 is located on the westbound side of Route 91 and is part of the overall Highway 60/91/215 Freeway Improvement Project. Wall 207 is located on the east side of the northbound lanes of Interstate 215 at the Chicago Avenue overpass.

Both Walls 119 and 207 were Type 1 retaining walls that had been specified as part of the widening project for Route 91. Though the joint venture between Caltrans and the CIWMB, Wall 119 was constructed in 2003 and Wall 207 was constructed in 2006. Both projects used tire-derived aggregate (TDA)  as an alternative to a conventional soil backfill material.

Using standard construction equipment, 837 tons of TDA (equivalent to 83,700 waste tires) was installed behind approximately 300 lineal feet of Wall 119 and 1,410 tons of TDA (equivalent to 141,000 waste tires) was installed behind approximately 300 lineal feet of Wall 207. To prevent soil infiltration into the TDA, a geotextile wrap was incorporated into the TDA placement. Two feet of cover soil was placed over the TDA backfill.

Wall 207 instrumentation cabinet.

The purpose of these projects was to demonstrate that the soil pressure exerted on a retaining wall could be reduced by 30 percent by placing TDA as a lightweight backfill material behind the wall. Both projects used TDA as a backfill material behind a standard Type 1 retaining wall. Monitoring instruments were installed in the walls during construction and measurements were taken to determine the reaction of the wall as compared to a typical retaining wall constructed with soil backfill.

The pilot project demonstrated that by using the TDA backfill, the pressure on the wall is reduced thereby allowing for an alternate wall design to be used which uses less concrete and/or steel and significantly reduces construction costs.

Instrumentation

Both walls were constructed with four instrumentation measurement stations that included stress/strain gauges, pressure sensors, temperature sensors and tilt meters. Three stations measure TDA-related values and the fourth station measures soil values as a comparative data point. Data loggers record the data from the instruments which is later down loaded to a laptop computer for analysis.

Pressure Cell Installation

The pressure cells were installed in custom concrete block casings prior to installation into the retaining wall. The retaining walls were poured in sections, as is typical of this type of retaining wall

Pressure cell placed in retaining wall.

Pressure cell placed in wall foundation.

 

Tilt meter being installed in wall.

Temperature Sensor Installation

The temperature sensors were installed directly into the TDA approximately three feet from the wall and at three different heights in order to monitor the temperature of the TDA fill.

Tilt Meter Installation

Four tilt meters were installed along the exterior side of the retaining walls (opposite from the backfilled side).

TDA Placement

Before placement of TDA began, an eight-ounce, non-woven geotextile fabric was placed on the subgrade and the cut slope. As the TDA was installed, the edge of the fabric along the cut slope was also raised until the TDA installation was complete. This secured the fabric on the subgrade and up the cut slope, ensuring that the soil was separated by the geotextile from the TDA. Before the cover soil and final two feet of TDA was placed, another geotextile piece was installed along the backfill side of the wall for anchorage.

For the Wall 119, about 837 tons of TDA were placed at an approximate rate of 90 tons per working day. The TDA was transported in 40-foot walking floor trailers. After each one-foot lift was placed (approximately 2-3 truckloads), the material was then compacted with a 10-ton smooth-drum vibrating roller. A minimum of six passes by the compactor were observed and recorded by the onsite construction manager.

TDA backfill wrapped in geotextile fabric.

TDA placement with standard heavy equipment.

 
Last updated: December 3, 2010