CDI Recycling Centers

  • No tonnage limit
  • No state minimum standards (SMS)

Storage Limits:

  • 30 day unprocessed
  • 1 year processed

Storage Plan May be Required

Tests:

  • Must meet 1-3 tests
  • Plus 4th part “separated at the point of generation”

Inert (Type A) Debris Recycling Centers

  • No tonnage limit
  • No state minimum standards

Storage Limits:

  • 6 months unprocessed
  • 18 months processed

Storage Plan May be Required

Tests:

  • Must meet 1-3 tests
  • Commingling “OK”

Small Volume CDI Processing Operation

  • EA notification (non-permit) required
  • Incoming tonnage under 25 tons per day
  • State minimum standards

Storage Limits :

  • 15 days unprocessed
  • 1 year processed

Plan Required

Tests:

  • Must meet 1 and 3 tests
  • Commingling “OK”

Medium Volume CDI Processing Operation

  • Registration permit required
  • Incoming tonnage at 25 tons per day (tpd) up to 175 TPD
  • State minimum standards apply plus facility SMS

Storage Limits:

  • 15 days unprocessed
  • 1 year processed

Plan Required

Tests:

  • Must meet 1 and 3 tests
  • Commingling “OK”

Large Volume CDI Operation

  • Full permit required
  • Incoming tonnage at 500 tons per day or more
  • State minimum standards apply plus facility SMS

Storage Limits:

  • 30 days unprocessed
  • 1 year processed

Report Required

Tests:

  • Must meet 1 and 3 tests
  • Commingling “OK”

Small Volume C&D Chipping & Grinding Operation

  • EA notification (non-permit) required
  • Incoming tonnage under 200 tons per day
  • State minimum standards apply

Storage Limits:

  • 30 days unprocessed
  • 90 days processed

Plan Required

Tests:

  • Must meet 1 and 3 tests

Large Volume C&D Chipping & Grinding Operation

  • Registration permit required
  • Incoming tonnage 200 tons per day or more
  • State minimum standards apply plus facility SMS

Storage Limits:

  • 30 days unprocessed
  • 90 days processed

Plan Required

Tests:

  • Must meet 1 and 3 tests

Inert Processing Operation (Type A)

  • EA notification (non-permit) required
  • Incoming tonnage under 1500 tons per day
  • State minimum standards apply

Storage Limits:

  • 6 months unprocessed
  • 18 months processed

Plan Required

Tests:

Must meet 1 and 3 tests

Inert Processing Facility (Types A&B)

  • Full permit required
  • Incoming tonnage at 1500 tons per day or more
  • State minimum standards apply plus facility SMS

Storage Limits:

  • 6 months unprocessed
  • 18 Months Processed

Report Required

Tests:

  • Must meet 1 and 3 tests