In addition to tracking the addition of new pages, this log contains the maintenance history of pages that have been changed or updated since the permit toolbox was first published in February 2001. For more information on maintenance of this Website, please visit the Toolbox Maintenance Kit or the Suggestion Box.

2022 | 2021 | 2020 | 2018 | 2017 | 2016 | 2015 | 2011 | 2010 | 2008 | 2007 | 2005 | 2004 | 2003 | 2002 | 2001

April 2022

October 2021

  • SB 1383 Solid Waste Facility Requirements Statewide Webinar YouTube (1:04:38). On February 4, 2021, from 9:00 AM – 10:00 AM, CalRecycle hosted a statewide webinar that covered the requirements for solid waste facilities. This webinar also included a question and answer session.

July 2021

June 2021

  • LEA Full Permit Process and Timelines. This webpage includes a table that illustrates the general tasks and timelines for LEA processing of a full permit. Recent changes to this webpage include adding updated regulations resulting from SB 1383.
  • Public Notice: Informational Meetings Conducted by Enforcement Agencies. This webpage provides information and resources on informational meeting requirements for enforcement agencies. Recent changes to this webpage include adding updated regulations resulting from SB 1383.
  • Full Permit Application and Permit Package. This webpage summarizes the application submittal elements (aka “Laundry List”) for any facility that is required to obtain a new, modified, or revised full permit. Recent changes to this webpage include adding updated regulations resulting from SB 1383.

May 2021

  • Permit Toolbox. The Permit Toolbox provides online tools and resources to provide guidance to local enforcement agencies (LEA), operators, applicants, and CalRecycle staff in obtaining, processing, and maintaining new and revised solid waste facility permits and completing other permit-related tasks and responsibilities. Recent changes to this webpage include adding quick menus in order to make navigation to other webpages easier and removing outdate information.
  • Permitting Transfer/Processing Operations and Facilities. This webpage provides information and resources for permitting transfer/processing operations and facilities. Recent changes to this webpage include adding updated regulations resulting from SB 1383.
  • Permitting Compostable Material Handling Facilities and Operations. This webpage provides information and resources for permitting compostable material handling operations and facilities. Recent changes to this webpage include adding updated regulations resulting from SB 1383.
  • Permitting In-vessel Digestion Operations and Facilities. This webpage provides information and resources for permitting in-vessel digestion operations and facilities. Recent changes to this webpage include adding updated regulations resulting from SB 1383.
  • Permitting Landfills and Disposal Sites. This webpage provides information and resources for permitting landfills and disposal sites. Recent changes to this webpage include adding updated regulations resulting from SB 1383.

March 2021

  • Regulation Implementation Guidance. This webpage provides links that Local Enforcement Agencies may find helpful in navigating some of the solid waste facility regulations. Recent changes to this webpage include adding links to the SB 1383 Frequently Asked Questions (FAQ’s) and detailed guidance that focuses on new measurement requirements for the transfer/processing, compostable materials and in-vessel digestion regulations.

May 2020

  • Questions and Answers: Compostable Materials Regulations. This webpage provides responses to questions regarding the compostable materials regulations. A new section on odor was added to this webpage.
  • Questions and Answers: In-vessel Digestion Regulations. This webpage provides responses to questions regarding the in-vessel digestion regulations. A new section on odor was added to this webpage.
  • Guidance for Enforcement Agencies (EAs) on Hosting Virtual Public Meetings. Unforeseen circumstances may sometimes make in-person informational meetings infeasible. CalRecycle encourages EAs to consider hosting virtual public meetings to engage with the public in order to comply with informational meeting requirements and to support the timely review of SWF permit applications.

January 2020

  • A Field Method for Estimating the Level of Physical Contamination in Compostable Material. This webpage is intended to provide guidance and serve as one method of meeting the physical contamination requirements of 14 CCR Sections 17862.1, 17868.3.1, and 17896.61

April 2018

August 2017

March 2017

  • Guidance: Emergency Waiver of Standards. This guidance provides local enforcement agencies (EA) and operators with information regarding the process for a solid waste facility operator to request a waiver of standards, permit terms and/or conditions to address changes needed to handle debris resulting from a declared emergency.

June 2016

  • Questions and Answers: In-Vessel Digestion Regulations. This webpage provides responses to questions regarding the in-vessel digestion regulations.”

May 2016

April 2016

  • Questions and Answers–Compostable Materials Regulations. This updated webpage provides responses to questions regarding the compostable materials regulations. New questions are added periodically.

March 2016

January 2016

June 2015

May 2015

  • LEA Guidance: Owner/Operator Change Processing Procedures. This guidance has been developed to help local enforcement agencies (LEAs) with the process associated with notice of a plan to sell, encumber, or convey a solid waste facility ownership and/or operation to a new owner or operator, and/or change the address of a solid waste facility owner and/or operator.

April 2015

February 2015

January 2011

February 2010

  • Writing a Solid Waste Facility Permit. This web page has been developed in coordination with LEAs and CalRecycle staff to provide guidance on how to write a solid waste facilities permit that is consistent with California Code of Regulation, Title 27 (27 CCR) and the Public Resources Code (PRC). This web page replaces LEA Advisory No. 57 and updates and clarifies information to reflect changes to the solid waste facilities permit application (CIWMB Form E-1-77) since the advisory was originally published in 1999.

November 2008

  • Guidance: Additional Storage of Recycled Materials at Solid Waste Facilities. This page provides guidance to help local enforcement agencies (LEA) and facility operators address the additional storage of recycled materials at solid waste facilities. The current economic slowdown is having a direct impact on solid waste facilities and their ability to move recycled materials off site to markets, resulting in an increasing need to store more processed material on site for longer periods of time.

April 2007

  • The Permit Implementation Regulations became effective on April 13, 2007.
  • Many Permit Toolbox pages have been updated to reflect the new regulations. A Summary of the Top-10 Changes provides a concise introduction to the new regulations, including links to updated Permit Toolbox Pages, links to the updated regulations, and links to other resources.

August 2005

June 2005

  • Added additional CEQA resources and guidance.

January 2005

December 2004

  • Any application filed after January 1, 2005, which requires the use of form E-1-77, must be filed with the revised application form.  For the full permit tier, this includes new or revised permits, permit exemptions,  permit review reports, and RFI amendments. Applicable pages in the Permit Toolbox have been updated. For more information, see the rulemaking archives and the December 15, 2004 all-LEA email.
  • Added link to the Public Hearing/Participation Tools from the Index and Full Permit Page (designed to provide resources for conducting AB 1497 hearings ).

October 2004

  • Compost Page: Added link to FAQ page, added two flowchart hand-outs to the resources, added link to recent LEA letter on compost fires, added links to chipping and grinding regulations, and added link to exempt compost site resources.
  • Landfill Page: Updated links to Federal EPA Subtitle D regulations, added link to waste tire monofill regulations, and added link to recently adopted inert disposal regulations.

September 2004

  • Clarified guidance on the Registration Permit page regarding the reference and  attachment of the completed application form to a registration permit when forwarded to CalRecycle by the LEA.
  • Updated maintenance pages to reflect approval of the latest Permit Toolbox priority task list.

July 2004

  • Updated Conformance Finding Page and Tier Task Chart: Added clarification that transfer stations which recover less than 5 percent of the volume of materials received for reuse or recycling do not need to meet the conformance finding requirements.
  • Updated Glossary and Definitions pages: Added a link to the Local Government Central Integrated Waste Management Glossary.

May 2004

April 2004

March 2004

Updated various pages to reflect AB 1497 changes to the permit process, including the increased application review timelines for revised permits from 30 to 60 days and requirement that LEAs hold public hearings for revised full permits and for all CDI permits.

February 2004

January 2004

  • Added “authorizing eligibility” Web tool to help LEAs and applicants comply with the requirement of the notification tier.
  • The EA Notification (CIWMB Form 169) was updated to include a list of “authorizing eligibility” citations on the back side.
  • Added a link from the compost page to a new Web page created to answer frequently asked questions about the implementation of the compost regulations.
  • Finished updating the various “permit type” pages to reflect the adopted Construction and Demolition/Inert Debris regulations.
  • Deleted all links to the rescinded LEA Advisory 12.
  • AB 1479, effective January 1, 2004, and all-LEA email providing interim guidance on implementing the provisions of AB 1497.

December 2003

  • Updated the Notification page and the RFI page to reflect new standards that require some sites in the notification tier to submit an “operations plan”.
  • Updated the closure requirements and links on the full permit “laundry list”.
  • Updated the table on the RFI page to reflect the new CDI regulations and added a printer friendly version of the table.

November 2003

October 2003

  • Updated the notification tier page to reflect new filing requirements that include documentation that the operator has notified the local planning department

August 2003

May 2003

  • Updated the Compost page: The old guidance has been removed from this page until it can be more thoroughly updated to reflect the contents of the new regulations. A notice has been inserted alerting users of the effective date of the new regs. The resources and links have been updated so that important sections of new regs can be easily located.
  • Updated the list of sites that qualify for each permit tier on the full, standardized, registration, and notification pages to reflect changes in the compost regulations.
  • Updated the RFI page: The chart has been updated to provide links to the new Report of Compost Site Information (RCSI) requirement and the new Odor Impact Minimization Plan (OIMP). Also added some links directly to the Transfer Station toolbox page and the Notification toolbox page.

April 2003

February 2003

  • Closure Regulations Effective 2/25/2003.

October 2002

September 2002

August 2002

  • Added Toolbox Search Engine. The link will be added to the vertical menu that appears on most pages.
  • Added 3 sample letters to the Sample Documents and Letters Page: 1 LEA Permit Issue Letter and 2 LEA Proposed Permit Cover Letters.
  • Updated the Permit Toolbox Maintenance Kit.
  • Added Web Page Review Guide and Form.
  • Added results of 2002 LEA Permit Toolbox Survey

July 2002

  • Added list of resources to the bottom of the 5-year Permit Review page.
  • Minor language changes to 5-year Permit Review page: 1) new links to the pages for processing full, standardized, and registration permits; 2) reminder that standardized permits will need to be submitted to the Board for concurrence.

June 2002

March 2002

February 2002

December 2001

October 2001

August 2001

  • Added a link to State Clearinghouse’s CEQA notification forms in the CEQA Resources.
  • LEA Advisory 21 and LEA Advisory 24 regarding permit review reports have been updated.
  • The solid waste facility permit template on the permit forms page has been updated to include instructions, drop down menus, and form fields.

July 2001

June 2001

  • Added Compost Page.
  • Added Sample Documents and Letters Page.
  • Updated Home Page Quick Menus.
  • Added links to Quick Menus and Samples Page to vertical menu bar (green column on left side of page).
  • Updated various links, wording, typos, and made other minor changes in response to LEA and P&E staff comments.